Twelve years of managing procurement budgets will teach you one thing fast: the sticker price is the least important number on the quote.
I run procurement for a mid-size refrigeration contractor. We spend around $180,000 a year on commercial refrigeration parts, components, and consumables. I've signed off on more Bohn condensing units, evaporator coils, and odd-size accessories than I want to count — and I've eaten the cost of a few bad calls along the way.
Here's the checklist I run through before any of those POs gets my signature. It's built for facility managers, mechanical contractors, and cold-storage builders who buy in volume and can't afford to get it wrong.
Seven steps. Number seven is the one almost nobody actually runs.
This is the most common mistake I see on inbound quotes. Someone sends a spec sheet for a "coil" without specifying which side of the system they mean, and three vendors quote three different products back. Now you're comparing apples to a completely different fruit.
The evaporator coil sits inside the refrigerated space — it absorbs heat from the box. The condenser coil sits outside (or in a remote rack) and rejects that heat to ambient air. They look similar in a catalog photo. They are not interchangeable. Refrigerant-side pressures, fin spacing, and defrost strategy are all different.
My rule: no quote leaves the building without a system diagram attached. If your team can't tell you which coil is on which side, the cost comparison is already worthless.
Checkpoint: Pull the refrigeration schematic and label the evaporator and the condenser before you open a single price sheet.
Bohn condensing units are not the cheapest on the page. They're also not the most expensive. But the purchase price is where the comparison starts, not where it ends.
For each unit, I force the comparison into a simple TCO spreadsheet. Rows I care about:
If you want the specs grounded in something verifiable, use Bohn's published catalogs and cut sheets directly. Their nomenclature tables and dimensional data are consistent, and that matters when you're cross-referencing an existing install. Verify current specs at bohn.com before you finalize a PO.
Also check the regulatory envelope. Per the U.S. Department of Energy's commercial refrigeration equipment standards (10 CFR Part 431), covered equipment sold in the U.S. has to meet minimum efficiency thresholds, and those thresholds get revised. Confirm current requirements at energy.gov before you lock the spec — a non-compliant unit is a return, not a saving.
Checkpoint: If the TCO spreadsheet isn't filled in for every vendor's quote, you're guessing, not comparing.
Here's something that took me three years to figure out: air filters are not a rounding error in refrigeration and HVAC budgets. They're a recurring cost that compounds when you buy cheap.
The conventional wisdom says buy the cheapest filter that fits the housing. My experience says that's how you get compressor cycling, higher discharge temps, and a spring service call you didn't budget for.
I now track filter spend as its own line. At our volume, that line is roughly $6,800 a year — about 4% of the total. But when we ran mid-tier pleated filters instead of the cheapest option, our filter-related callback rate dropped enough to cover the price difference twice over. That's a fact I can defend in a budget meeting.
Checkpoint: Know your MERV requirement for the application before you shop on price. A cheap filter with the wrong MERV is either useless or a restriction — neither one helps.
This is the step most procurement checklists miss entirely.
When you spec a refrigeration system, you're not just specifying the equipment — you're specifying the environment it lives in. If the mechanical room, maintenance bay, or service garage is unheated, you've created a cold-weather problem that doesn't show up on the equipment quote.
Two questions I always ask now. First, is the workspace going to stay above freezing during winter service windows? Second, do we have a garage heater specified for the bay where the truck and recovery equipment sit? Nothing impressive about a garage heater — until the one week a year your crew can't do an emergency repair because the bay is at 28°F and the tools won't hold a charge. We specified a modest unit heater for the bay, and it paid for itself in avoided downtime and fewer frozen-line callbacks.
Checkpoint: Walk the install site in winter before you finalize the quote. If you wouldn't want to work in that room in January, your techs won't either.
Bohn's documentation is genuinely good — nomenclature tables, wiring diagrams, selection software, service bulletins. It's one of the reasons their equipment holds up in the field.
But "documentation exists" and "your team can use it" are two different things. Before I approve a purchase, I hand the wiring diagram to the lead tech and ask one question: could you troubleshoot this without calling the vendor? If the answer is no, we either schedule training, pick a different configuration, or accept that the first service call is going to have a learning curve baked in. All three are legitimate outcomes. What isn't legitimate is pretending the documentation doesn't matter because it wasn't included in the price comparison.
Checkpoint: Pull the wiring diagram for the exact model you're buying before the order. If you can't find it now, you'll be hunting for it during the first breakdown.
This is where trust is either built or broken.
I've learned to ask "what's not included?" before I ask "what's the price?" Every single time. After the third time a "final" invoice came in higher than the quote, I stopped trusting verbal scope confirmations entirely.
Here's why. In Q2 2024, we got two quotes for a condensing unit replacement at one of our cold-storage accounts. Vendor A came in at $11,400. Vendor B came in at $10,600. On paper, B was the obvious pick — about 7% cheaper.
Then I called Vendor A back and asked for the all-in number with everything itemized. They came back at $11,400 all day: freight, startup, warranty, everything. Vendor B's initial quote did not include a $680 rigging fee, a $340 warranty extension, and an $890 startup charge — all of which "weren't standard." Total for B: $12,510. That's a 9.7% gap in favor of the vendor who looked more expensive.
That number sits in my head because it's not unusual. The vendor who lists every fee upfront — even when the total looks higher — usually costs less in the end. Not because they're nicer, but because they don't have room to add surprises after the signature.
If a quote doesn't itemize freight, rigging, startup, and warranty separately, ask for a revised one. If the vendor can't or won't, that's your answer.
We keep a simple spreadsheet: order date, vendor, line items, quoted price, final invoice, delta, and the reason for the delta.
If I remember correctly, our first year of tracking showed about 22% of orders with some variance between quote and invoice. Most of it was small — a freight adjustment, a substituted part, a small labor add. But the accumulating pattern was the point. It gave me a factual basis for renegotiating terms with two vendors and cutting the mystery line items almost entirely.
We've done maybe 400 orders in that tracker now. I want to say 380, but I'd have to open the file. The number itself isn't the point — it's that we have the number at all.
Checkpoint: If you can't pull up twelve months of orders and see quote-vs-invoice for each one, you're starting the review from zero every year.
A few patterns I've watched repeat across teams and companies:
None of these are exotic. They're the basics — which is exactly why they keep showing up.
Data points referenced above reflect our internal tracking as of Q1 2025. Confirm current DOE requirements at energy.gov and current Bohn product specs at bohn.com before finalizing any purchase.